    Last Updated: 10/28/2022

    Project Overview and Objectives

    The objective of this project is to complete a wet check so as to identify and document issues so that HydroPoint can convey all repairs needed to the customer in a complete and comprehensive fashion.  

    Scope of Work

    The CONTRACTOR shall access the Station Assessment Form by going to  www.hydropoint.com/psforms on their mobile device. Click on Station Assessment Form and this will open the link in to Record Information and Remove Existing Controller: 

    Station Assessment Form

    The CONTRACTOR shall use the Station Assessment Form and complete a system and station by station inspection after pressurizing the system.  Operate each station and document condition in the wet check form.  Note each item for repair and take a photo within the wet check form.  Once all stations have been operated and form is complete, submit the form.

    Wet Check Issues

    The CONTRACTOR shall use the Station Assessment from found at www.hydropoint.com/psforms to document the following repair issues for each station. Any other issues found should be documented in the note fields.

    • Mainline Break 
    • Lateral Line Break 
    • Broken Head – note brand and size
    • Clogged Nozzle 
    • Blocked Head – note brand and size if taller head required
    • Over-spraying heads


    Project Administration

    Work Orders

    After this scope of work has been signed and accepted by the CONTRACTOR, and prior to the project starting, the Project Manager will issue a work order for each site to be assessed by the CONTRACTOR.   The work order shall include specifics for each site, including the number and locations of each site to be assessed, specific timing requirements, and pricing specifics.   

    Any adjustments to the scope of work to be performed, whether initiated by HydroPoint or as a result of site conditions discovered before or during the site assessment, must include an amended or additional work order, as determined by the Project Manager. All adjustments to the scope shall be communicated in writing.  

    Pricing

    Pricing for this project will be based on the pricing schedule included with the Work Order. Any expense above or beyond the pricing detail in the Work Order must have a request submitted to and approved by the Project Manager.

    Invoicing

    Invoices should be sent to apbilling@hydropoint.com; copying the Project Manager. Invoice approval is subject to verification of work completed and HydroPoint’s receipt of a valid SAR. Payment terms are NET30 from date of invoice approval. 

    Invoices must reference the work order for each site when submitted to HydroPoint for payment. Invoices will not be paid unless a work order is referenced for each site on the invoice. Example Invoice:

    Graphical user interface, application

Description automatically generated

    In the example invoice above, the yellow highlighted sections reflect the important elements that need to be provided on each invoice.  These include:

    • HydroPoint work order number
    • Job/project name
    • Dates of the field work
    • Activity - Line item breakout including quantities
    • Comments and Notes

    Invoices must be submitted within three (3) business days after the conclusion of the project. The CONTRACTOR may opt to submit invoices before a total project is complete, as sites within the project are completed.

    Contacting HydroPoint Professional Services

    The HydroPoint Professional Services Team has grown to better support you and our customers.   You can reach the HydroPoint Professional Services team by calling 707-285-3250.

    • Choose Option 1 for the Project Management Team
    • Choose Option 2 for WeatherTRAK Installation Support

    Schedule Changes

    We understand that there will be things that come up that will impact your projected schedules like weather, traffic, personal issues etc. You must notify the project manager as soon as you determine there will be a change in your schedule so that the customer can be notified. This applies to ANY schedule change including moving an installation date up in your schedule, as well as any delays.

    Code of Conduct

    While on site performing services for HydroPoint, you are representing the company as our Certified Service Provider. Please dress and act like a professional, keep your work area tidy, no radios, no cursing, no spitting, and no offensive clothing. If you must interact with a  customer or customer tenant, be polite. Regardless of the condition of the irrigation system or the existing controller, refrain from calling out the poor quality of maintenance to a customer or tenant. If you find unsafe or not-to-code conditions, you should point these out to the site manager, noting that you found an unsafe or not-to-code situation. Record this info and who you spoke to in your report. Escalate unsafe conditions to the Project Support Team as you find them.

    As appropriate, please use safety cones to mark off your work area to keep people out. Take care to avoid creating tripping or other safety hazards around your workspace. Before you leave your workspace, make sure you have picked up all trash and debris and dispose of them properly by using a trash bin. Review the any additional Customer Safety Standards.  Make sure any employees you have working on a the site understand the Code of Conduct and the afore mentioned Safety Standards.