    WeatherTRAK Controller Recommissioning

    Scope of Work (HP-PS-SOW-WT-RCMN (WT Recommssion)

    PDF es:

    Last Updated: 10/28/2022

    Project Overview and Objectives

    The objective of this Scope of Work is to recommission one or more WeatherTRAK controller(s), ensure the controller is online and connected to WeatherTRAK.net and properly programmed, and then complete a station by station inspection, (“Wet Check”) and provide the CUSTOMER with a detailed reporting of the operational status of the controller, related accessories, and station inspection results at each location. The result of this reporting will be in the format of a Controller Installation Report (CIR). HydroPoint will provide the CIR directly to the CUSTOMER and will also use the information gathered to confirm the WeatherTRAK controller is programmed correctly.   

    Scope of Work

    Upon acceptance of this project, the CONTRACTOR agrees to complete all aspects of the work described in this scope of work and to verify that all points of information requested are thoroughly and completely submitted via the specified collection tool, and according to the timeline outlined herein.  

    The CONTRACTOR agrees to thoroughly and promptly communicate with the assigned HydroPoint Professional Services Project Manager regarding all aspects of the project. The project deliverables shall be completed for each site and will be verified by HydroPoint Professional Services via the submitted CIR and weathertrak.net.  

    The Site or Sites on which work are to be performed are listed in the work order(s) that will be provided to the CONTRACTOR. 

    Pre-installation

    The CONTRACTOR shall check-in with the site manager before beginning any work and shall check out with the site manager when work is complete.  In some cases, an alternate check-in/out process may be required (this process will be communicated in writing). Any urgent or significant issues found during the recommissioning should be escalated to the site manager and to HydroPoint Project Manager before departing the site AND thoroughly documented in the Controller Installation Report (CIR) form; for example: a mainline break.

    The CONTRACTOR shall review the CUSTOMER’S Safety Standards (where applicable) and ensure compliance with those standards while on site.

     The CONTRACTOR shall access the CIR Form by going to  www.hydropoint.com/psforms on their mobile device. The Contractor shall select "Controller Recommissioning" from the Scope of Work Field.

     Inspect the WeatherTRAK Controller

    1. Do the following when inspecting the controller: 
      • Ensure that all 120v service lines are in conduit.
      • Verify that all active 24v station field wires are securely connected to station terminals.
    2. Check for rain sensors ensure that: 
      • Rain sensors are installed in sensible places that will capture rainwater effectively without overhead interference and with receivers mounted outside of any metal enclosures.  Note any issues.
      • Rain sensor wires are connected to the RS port on the controller using instructions for Normally Closed then test the rain sensor per manufacturer's instructions.

    Program the Controller

    1. Confirm Controller is online by reviewing the Microzone and Subscription Date. The Microzone should NOT read “12345678” and Subscription should NOT read 01/01/2005. 
    2. Programming stations is best done from the WeatherTRAK Mobile app. Follow the prompts in the app to get started. Programming can also be done from the controller interface. Read the WeatherTRAK Controller User Guide for instructions and more information. All controllers arrive pre-activated so they will be ready for programming. 
    3. The following should be completed with the WeatherTRAK Mobile App: Follow the prompts in the mobile app to complete the set-up and station programming. Ensure each of the following is completed:
      1. Complete initial set-up with date, time, time-zone, max active stations and master valve setting.
      2. Enter desired water day patterns, start times and water windows to meet site needs.
      3. Program WeatherTRAK controller in Automated Mode by setting each station to Auto and then entering data from Program Worksheets, Sprinkler type, soil type, plant type, sun exposure and slope (precipitation rate and root depth are adjustable for maximum conservation).
      4. All stations should be named.
      5. Place geolocation Pins for each of the following Controller, Rain Sensor, Backflow, Master Valve and Flow Sensor.   (FS/MV where applicable)
      6. Place geolocation Station Location Pins for each station

        •  

    Test the System

    1. Test the system to ensure that all stations are active. 
    2. Run a valve test and make note of any stations showing shorts or no-connects.
    3. Go to the Alerts screen and verify that there are no alerts.  If there are Alerts present troubleshoot / modify settings as needed or call contractor support to receive guidance on dealing with the alerts.
    4. Verify controller is activated and online.

    Final Inspection

    1. Complete the Wet Check section by operating each station and documenting each issue found by selecting issue and taking a photo of each issue. This is done for all stations.
      • Document any other site issues in the Other Site Conditions section.
    2. Submit the CIR + Wet Check form while on site.

     

    Project Administration

    Work Orders

    After this scope of work has been signed and accepted by the CONTRACTOR, and prior to the project starting, the Project Manager will issue a work order for each site to be assessed by the CONTRACTOR.   The work order shall include specifics for each site, including the number and locations of each site to be assessed, specific timing requirements, and pricing specifics.   

    Any adjustments to the scope of work to be performed, whether initiated by HydroPoint or as a result of site conditions discovered before or during the site assessment, must include an amended or additional work order, as determined by the Project Manager. All adjustments to the scope shall be communicated in writing.  

    Pricing

    Pricing for this project will be based on the pricing schedule included with the Work Order. Any expense above or beyond the pricing detail in the Work Order must have a request submitted to and approved by the Project Manager.

    Invoicing

    Invoices should be sent to apbilling@hydropoint.com; copying the Project Manager. Invoice approval is subject to verification of work completed and HydroPoint’s receipt of a valid SAR. Payment terms are NET30 from date of invoice approval. 

    Invoices must reference the work order for each site when submitted to HydroPoint for payment. Invoices will not be paid unless a work order is referenced for each site on the invoice. Example Invoice:

    Graphical user interface, application

Description automatically generated

    In the example invoice above, the yellow highlighted sections reflect the important elements that need to be provided on each invoice.  These include:

    • HydroPoint work order number
    • Job/project name
    • Dates of the field work
    • Activity - Line item breakout including quantities
    • Comments and Notes

    Invoices must be submitted within three (3) business days after the conclusion of the project. The CONTRACTOR may opt to submit invoices before a total project is complete, as sites within the project are completed.

    Contacting HydroPoint Professional Services

    The HydroPoint Professional Services Team has grown to better support you and our customers.   You can reach the HydroPoint Professional Services team by calling 707-285-3250.

    • Choose Option 1 for the Project Management Team
    • Choose Option 2 for WeatherTRAK Installation Support

    Schedule Changes

    We understand that there will be things that come up that will impact your projected schedules like weather, traffic, personal issues etc. You must notify the project manager as soon as you determine there will be a change in your schedule so that the customer can be notified. This applies to ANY schedule change including moving an installation date up in your schedule, as well as any delays.

    Code of Conduct

    While on site performing services for HydroPoint, you are representing the company as our Certified Service Provider. Please dress and act like a professional, keep your work area tidy, no radios, no cursing, no spitting, and no offensive clothing. If you must interact with a  customer or customer tenant, be polite. Regardless of the condition of the irrigation system or the existing controller, refrain from calling out the poor quality of maintenance to a customer or tenant. If you find unsafe or not-to-code conditions, you should point these out to the site manager, noting that you found an unsafe or not-to-code situation. Record this info and who you spoke to in your report. Escalate unsafe conditions to the Project Support Team as you find them.

    As appropriate, please use safety cones to mark off your work area to keep people out. Take care to avoid creating tripping or other safety hazards around your workspace. Before you leave your workspace, make sure you have picked up all trash and debris and dispose of them properly by using a trash bin. Review the any additional Customer Safety Standards.  Make sure any employees you have working on a the site understand the Code of Conduct and the afore mentioned Safety Standards.